Phase 1
Phase 2
Location: Five-Corners Intersection; East Fifth Avenue and Pioneer Way
Date: Project is planned to start 7 a.m., Monday, March 14
Duration: About six weeks
Traffic Impact: Reduced number of lanes through the intersection along Pioneer Way and detours. Expect long delays. Please use an alternate route if possible. Phase 1 should last for about one week. Phase 2 is planned to begin on Monday, March 21 and will last for about four to five weeks.
Contact Name: Mark Beaulieu
Contact Phone: 509-764-3776