Posted on: March 8, 2022

Temporary traffic revisions for sewer repairs expected to start March 14

Phase 1 

Phase 1Phase 2Phase 2

Location:             Five-Corners Intersection; East Fifth Avenue and Pioneer Way

 

Date:                    Project is planned to start 7 a.m., Monday, March 14

 

Duration:             About six weeks        

 

Traffic Impact:   Reduced number of lanes through the intersection along Pioneer Way and detours.  Expect long delays.  Please use an alternate route if possible. Phase 1 should last for about one week. Phase 2 is planned to begin on Monday, March 21 and will last for about four to five weeks. 

 

Contact Name:  Mark Beaulieu

 

Contact Phone: 509-764-3776